Interested in connecting a generation facility to our power grid? This means you’re looking to:
- offset your power use
- add, replace, or modify a generator
Get an Exploratory Estimate
We offer the Exploratory Study as an option to assess the feasibility of your potential generation at a conceptual level.
Learn more about the process and apply below.
Processing Time: 15 calendar days
Review the Exploratory Study process and submit an Exploratory Study Application by emailing us.
The fee for the study is $5,000 plus taxes
Processing Time: 45 calendar days
We’ll begin the study and develop a draft report.
You’ll review the draft report and submit questions to us within 15 days of receiving the report. At your request, we can meet with you to review the draft.
We’ll develop and provide you with the finalized report.
After reviewing the report, if this is something you’d like to proceed with please begin the Standard Generator Interconnection Procedure.
How to Connect a Generation Facility
We’ve developed the Standard Generation Interconnection Procedure (SGIP) to assist you in understanding the process required to interconnect a generator to the transmission system.
Projects 1 MW or More – Voltage Level Greater Than or Equal to 25 kV
If you’re looking to connect a facility with a generating capacity of 1 MW or more, please review the procedure below.
Processing Time: 15 calendar days
Review the SGIP process and submit the Interconnection Request application. This includes a non-refundable $15,000 deposit. Once completed, email us.
We’ll review your application. If any information is missing, it must be submitted before moving to the next stage. You’ll also be assigned a queue position.
Processing Time: 90 calendar days
You have the option to complete a Feasibility Study for your proposed project before deciding to move on to the System Impact Study. You’ll sign and return the agreement.
A deposit of $15,000 is required.
Processing Time: 120 calendar days
You’ll sign and return the agreement. You’ll also submit the deposit amount relevant to your project:
- <20MW $50,000
- 20MW to 50MW $75,000
- 50MW to 150MW $100,000
- >150MW $150,000
This will provide an optional study based on the results of the System Impact Study.
A deposit of $30,000 is required.
Processing Time: 270 calendar days
We’ll complete a Facilities Study for the project. You’ll need to provide written permission for us to proceed.
A deposit of $150,000 is required.
Processing Time: 140 calendar days
We’ll provide a draft of the agreement and appendices. You may request to negotiate the appendices before we complete the final agreement.
You’ll sign and return the agreement.