Make a street a little brighter.

We can add, remove or move SaskPower streetlights at the request of the party paying the monthly bill. Developers needing lighting for new subdivisions may also submit requests.

What are the steps?

  1. Application
  2. Design (7-14 days)
  3. Written Quote (2 days)
  4. Confirmation
  5. Approvals (10-30+ days)
  6. Construction (10-30+ days)

APPLY NOW

If you need more information, please view our Adding and Removing Streetlights PDF.

 

Dart Image
Provide Your Feedback